Erect Two Modular Distillation Columns – Gantry Rigging

Project Details

  • Project: Off-load and erect two fully prefabricated distillation column modules weighing 58,000 lbs each, within an actively processing pharmaceutical environment.

  • Equipment used: 300 ton hydraulic gantry, two (2) Versa-Lift™ 60/80’s and jockey tractor

  • Date: January 2017

Scope Of Work:

Off-load and erect two (2) fully prefabricated distillation column modules within an actively processing pharmaceutical environment. The heavy rigging project was completed in two phases, seven (7) weeks apart; each phase being one module.  Each 58,000lb. module was brought into the building on its side through an enlarged, grade-level temporary wall penetration. The modules were then up-ended into their operating position using 300 ton telescoping gantry and lowered onto anchor bolts in a recessed floor area.

Rigging a pharmaceutical distillation column module within near-zero clearance environment using 300 ton hydraulic gantry system

The two phases were required to be sequenced in non-preferred order with the first module installed being the once closest to the wall penetration. This created a more restricted ingress and tighter clearances to erect the second module. For both modules, the gantries operated with zero overhead clearance for the tilt-up. Primary equipment consisted of 300 ton hydraulic gantry, two (2) Versa-Lift™ 60/80’s and a jockey tractor.

Project:

  • Two (2) modules; each 13ft. x 14ft. x 34ft. and weighing 58,000lb.
  • Two separate phases/mobilizations
  • Unload, position, erect, level and anchor modules in place
  • Erection required gantry extension to 37ft. limit
  • Zero overhead clearance with full gantry extension
  • Cribbed & plated pit area for module erection

Unique Challenges:

Severely restricted clearances through the wall penetration and into position for upending; particularly with regard to the second module which was placed behind the first (first module was already in position between second module and wall penetration).

To up-end the columns and gain enough height to rotate the columns to their vertical position, the gantry posts were extended.  The extension equaled a full 37ft. height extension and zero clearance existed between the lift beam and overhead obstructions.

Share

Lowering 14,500 lb. low-headroom lift truck into basement area using a Versa-Lift™ Model 25/35 with boom hoist attachment. Note the Versa-Lift™ is on a cribbed and plated platform level with the floor, enabling the lift to access the opening.Cooler Infeed/Outfeed Remove & Replace – Power Generation
Relocating college print shopRelocation Of College Print Shop Equipment